Jurong Cable Tunnel
Pioneer, Singapore
Completion Year: 2018
Located 80 m below ground level, the Jurong Cable Tunnel is the deepest bored tunnel connecting mainland to a proposed island substation.
Location
Main Application
Civil Engineering
Project participants
Customer: Penta Ocean Construction Co., Ltd
The Project
Impressions from the project process
The first phase of the construction work with PEP Ergo Props used for supporting loads.
No anchorage is allowed on site with the existing structure.
Both VARIO GT 24 Girder Wall Formwork & MULTIPROP are used in this project.
MULTIPROP are used to support the loads of the structure for the uplift forces.
VARIO GT 24 Girder Wall Formwork are used for casting of the circular tunnel wall.
The first phase of the construction work with PEP Ergo Props used for supporting loads.
No anchorage is allowed on site with the existing structure.
Both VARIO GT 24 Girder Wall Formwork & MULTIPROP are used in this project.
MULTIPROP are used to support the loads of the structure for the uplift forces.
VARIO GT 24 Girder Wall Formwork are used for casting of the circular tunnel wall.
Are you working on a project like this?
Contact us – we will be happy to help you.